11
• Push bogie truck (1) onto C-rail (2).
• Slot two C-rails (1) into connecting element (2) and push together as
far as they will go.
• Hook tensioner (1) in chain (2) and turn it 90°. Insert connecting
element (6) and push tensioner (1) through it. Place plain washer (5)
and spring (4) onto the tensioning bolt (3) and screw it into the
tensioner (1).
• Tighten chain until the mark (arrow) is reached.
• Do not tighten on this side, as the unit is supplied pre-tensioned.
7
6
Selection of installation option
Select the desired installation option. For option (B), change the
position of power supply unit.
Caution for sprint and duo!
The plastic chain case is not packaging - do not remove!
Pre-assembly for installation
options A/C
Dispose of packaging material according to the applicable
statutory regulations.
• Remove the operator from its packaging.
• Release the switch trigger (1) and move it in the direction of the
arrow. Open the chain case (2).
• Slide the trolley (1) onto the chain (2) with the chain case (4). The
chain (2) engages in the chain wheel (3). If the chain wheel (3) does
not turn, pull the emergency release (N) once. The chain wheel (3) is
released.